<< Click to Display Table of Contents >> Navigation: Misc Application Notes > Optimis Clipboard Support |
There is a global setting that needs to be enabled (on the quotes tab) for this to work. Only enable this if you are using the Optimis ERP.
When quoting, when a quote recalculate is performed, Primecut automatically copies the Customer, grade, thickness, OC and MC to the clipboard ready to be pasted into Optimis FOR THE FIRST LINE ITEM.
If there are multiple line items in quote you can also select a line item, and choose OPTIMIS Copy to Clipboard.
OC (Operational Costs) and MC (Material Costs) are defined per unit part, so if quantities are defined on the parts, they are divided by the quantity to get "sell each" values.
OC is composed of:
Machine Time sell + Cutting/Consumable sell + Extra Charges sell + Adjustments
(Adjustment accrue when the sell price is manually fixed, can result in a negative OC as a result)